Project Description:
The Allen Training Complex at the University of Nebraska – Lincoln is a 46,000 square-foot facility, located northwest of the Bob Devaney Sports Center. Practice gyms, locker rooms, team meeting rooms, athletic therapy areas and offices for both the Husker men’s and women’s gymnastics programs are included in the complex.
Concrete Industries supplied 24,000 square feet of precast concrete walls, consisting of 10″ insulated prestressed concrete wall panels and 8″ solid prestressed concrete wall panels.
Ready Mixed Concrete, another NEBCO, Inc. company was also on site doing multiple concrete pours throughout the project. Roughly 3,500 cubic yards was poured over the duration of the project.
The Clark Enersen Partners were the architects on the project.